Reference Schedule of design documentation deliveries prepared by Hydrocoop Ltd. in the field of water supply systems

The list includes finished significant project documentation (PD) of greater extent.

Title of the PD: level of the documentation, description Employer Informative capital costs
Gajary – Water supply system 2nd stage:
PD for construction permit,
6,000 m of distribution mains and house connection branches DN 150 and DN 100
Municipal Office Gajary
728,000.-
Group water supply system Senica – Feeder pipeline „B“ for the villages Kuklov, Borský Svätý Jur, Sekule and Moravský Svätý Ján:
PD for construction permit and for realization 
Waterworks of Bratislava.
  1,892,050.-
Basin of Váh and Danube, agglomeration Galanta – Wastewater collection and treatment + Drinking water supply system –
Preliminary project,
4,799 m of water mains, water tanks 1 x 1,200 m3 and 2 x 3,000 m3
Waterworks of West Slovakia   1,991,600.-
Basin of Váh and Danube, agglomeration Šamorín – Wastewater collection and treatment + drinking water supply system,
Preliminary project,
50,171 m of water mains, water tanks                
Waterworks of West Slovakia
  5,924,220.-
Object of water supply system – group water supply system Gabčíkovo – Water source extension in the locality „A“:
Project within the Cohesion Fund,
water source extension by 6 wells, increase of pumping station capacity by Q = 500 l/s
Waterworks of West Slovakia
  8,911,240.-
Water supply system, Wastewater collection and treatment in the region Dolné Kysuce:
PD for zoning and for construction permit
7,930 m of feeder lines, 1,580 m of inlet line to the water tank,
2,184 m of water distribution lines, 1 lifting station
Waterworks of North Slovakia..
62,921,000.-
incl. the sewerage syst.
Spišská Belá – Environmental infrastructure:
PD for zoning, for construction permit and for realization
4,464 m of feeder lines, 932 m of water distribution lines
The town Spišská Belá, 11,315,340.-
Chorvátsky Grob – Čierna voda, Feeder piping Rybničná – Šúr channel:
PD for zoning and planning decision and for realization
2,080 m of piping DN 400
The village Chorvátsky Grob      858,000.-
Viničné – Water supply system reconstruction:
PD for zoning and planning decision and for construction permit, 1,285 m of DN 150, 668 m of DN 100, 130 m of house connection branches
Waterworks of Bratislava      768,515.-
Modra – Vajnorská street – Water mains reconstruction:
PD for construction permit and for realization,
463,8 m of supply lines DN 100, 18 pcs of house connection branches
Waterworks of Bratislava      185,440.-
Reconstruction of technological and electro-technological part ofthe PS Trstená na Ostrove:
PD for construction permit and for realization,
exchange of pumps, structural adjustments in the PS
Waterworks of West Slovakia       46,120.-
The region Želiezovce – Drinking water supply system:
PD for construction permit,
24,135 m of feeder lines, 17,959 m of supply lines, 15,965 m of distribution mains, water tanks 2 x 4,500 m3, 2 x 400 m3
Waterworks of West Slovakia 15,650,000.-